CEB's shocking tender benders
|

Ceylon Electricity Board Head Office
in Colombo (inset) John Seneviratne |
By Frederica Jansz
A multi million rupee tender for aluminium
cables to be supplied to the Ceylon
Electricity Board has been recommended to be
awarded to Kelani Cables PLC despite the
company bid being higher than the lowest
offer by a massive Rs. 34 million.
Out of five selected bidders Kelani Cables
was the fourth highest in price but
nevertheless has been recommended the award
by both a Technical Evaluation Committee and
a Cabinet Appointed Procurement Committee.
The exact difference in price between Kelani
Cables and the lowest bid tendered by Alucop
Cables Ltd., is Rs. 34,856,635.
The Ceylon Electricity Board on November 6,
last year floated a tender for the "Supply
and Delivery of Conductors of All Aluminium
(FLY)." The amount required is 1400 metric
tonnes. Aluminium conductor cables are a
specific type of high-capacity,
high-strength stranded cable used inoverhead
power lines. The outer strands areof
aluminum, chosen for its excellent
conductivity, low weight, and low cost. The
centre strand is ofsteel, providing extra
strength.
Tender for aluminium cables
The tender for 1400MT of aluminium cables
closed on December 3, 2008. At the closing,
the results of the tender were; Alucop
Cables Rs. 382,934,005, APAR Industries Ltd
(India) Rs. 385,255,787, ACL Cables PLC Rs.
402,177,155, Kelani Cables PLC Rs.
417,790,640, and PEC Ltd. (India) Rs.
477,433,551.
On January 22 this year, the Ministry of
Power and Energy informed the shortlisted
bidders that the Cabinet Appointed
Procurement Committee (CAPM) had recommended
the award to be given to Kelani Cables PLC
despite the fact that Kelani Cables was the
fourth highest amongst the tenderers. The
price for the large quantity of 1400 metric
tonnes of cable quoted by Kelani Cables at
Rs. 417,790,640 is even higher than that
offered by its sister company, ACL Cables
PLC.
Interestingly, Alucop Cables were awarded
the tender for the identical requirement in
August 2007 and successfully completed their
supply over the required time frame of nine
months. The company however was rejected
this time despite having submitted the
lowest bid.
Managing Director, Alucop Cables, Shamendra
Panditha said the company had no complaints
of any kind from the CEB during the entire
nine months it supplied aluminium cables
after being awarded the tender in 2007.
"Why we were not chosen this time too since
we were not only the lowest in price but
have previously supplied and successfully
completed the tender last time I don't
understand," Panditha said.
Appeal against the tender
Panditha has been told by Ministry Secretary
J. M. K. Jayasekera that if they wish to
make any appeal against the tender being
awarded to Kelani Cables they can do so to
the Procurement Appeal Board.
This Shamendra Panditha did. On January 26,
he wrote to the Procurement Appeal Board
complaining that "the abysmal failure to
adduce reasons to even pro forma justify the
purported decision to award the said tender
to M/s Kelani Cables Limited, whose bid was
Rs. 34,856,644 higher than the bid submitted
by us, clearly demonstrates the fact that
the said purported decision was not in fact
supported by any legitimate and/or rational
reasons."
Panditha further asserts that Alucop had
previously supplied substantial quantities
of the said product to the CEB, from time to
time, during the past 25 years. "The said
supplies were effected on previously awarded
tenders, subject to the terms, conditions
and specifications stipulated in the said
tenders, to the entire satisfaction of the
CEB," he said.
Managing Director of the chosen bidder,
Kelani Cables PLC, Hemantha Perera
responding said, "Alucop Cables may have
been the lowest in terms of pricing but
probably they failed in some form or another
as far as specifications or other required
documentation was concerned. Which is why
we were chosen."
Also cheaper in price
Asked why Kelani Cables had been chosen even
over their sister company, ACL Cables, which
was also cheaper in price, Perera said he
did not know.
The irony is that a mere one year ago,
Perera himself was a disgruntled man -
complaining that he and his company Kelani
Cables had been unfairly muscled out of a
bid calling for the manufacture of single
phase electricity meters.
Exactly one year ago in January 2008, the
Ministry for Power and Energy riding
roughshod over the CEB secured cabinet
approval to bring in a Chinese company to
function as a joint venture partner with
LECO to manufacture locally, electrical
meters for the CEB.
The Chinese company was given the green
light for the manufacture, supervision and
purchase of these meters which the CEB is
now compelled to buy for the next 20 years.
A complete monopoly for the supply of a
minimum of 500,000 electrical meters per
year, to the CEB and LECO. At the time
other tenderers including Kelani Cables were
unceremoniously given the pushover despite
the fact that their offer was cheaper.
Meanwhile, Senior Assistant Secretary
(Tenders), Ministry of Power and Energy, J.
M. K. Jayasekara when contacted and asked on
what basis Kelani Cables was chosen at a
cost of Rs. 34 million more than the lowest
offer from Alucop said he could not even
remember signing a letter dated January 22,
2009 which was sent to four other
shortlisted tenderers informing them that
Kelani Cables had been recommended for the
award.
When The Sunday Leader spoke with
Jayasekera it was less than a week since he
had signed the letter in question concerning
a tender award running into over Rs.400
million. "I sign so many letters in a week
- I simply cannot remember this one," he
said. We reproduce below this letter.
Bid for Supply and Delivery of Conductor All
Aluminum (fly) 7/3,40mm - 1400 MT
Bid No: R3/P&D/ICB/C/2008/53-C
I wish to inform you that the Cabinet
Appointed Procurement Committee (CAPC) has
recommended to award the above bid to M/s
Kelani Cables Limited, P.O.Box 14, Wewelduwa,
Kelaniya.
Any representations against this
recommendation of the CAPC could be made to
the Procurement Appeal Board (PAB)
established at the Presidential Secretariat,
within one week, in accordance with Clause
8.3 of the Procurement Guideline 2006 (Good
& Works) of Sri Lanka with copies to General
Manager, CEB and Secretary, Ministry of
Power and Energy.
J.M.K. Jayasekera
Senior Asst. Secretary (Tenders)
For Secretary
Ministry of Power & Energy
This is just the tip of the iceberg as to
what goes on at the CEB. Here are some of
the other multi billion rupee scams that
have surfaced in the CEB and the Ministry of
Power & Energy in the last year.
Kerawalapitiya
The Ministry of Power and Energy together
with the Ceylon Electricity Board (CEB) in
this instance ignored all procurement
guidelines by the National Procurement
Agency (NPA) of which statute President
Mahinda Rajapakse no less is a signatory,
and dipped its fingers into EPTF/ETF funds
to finance the multi billion rupee combined
cycle power plant at Kerawalapitiya.
In addition to ignoring the NPA, the Power
and Energy Ministry also bypassed tender
procedures and offers of inward investment,
and instead granted the project to
Lakdhanavi Ltd., which is a local subsidiary
of Lanka Transformers Ltd, which in turn is
a subsidiary of the CEB.
Bankrupt, yet ignoring investment offers,
lobbying instead for a local partner
company, the government not only dipped its
fingers into EPF/ETF funds to the tune of Rs.
6,480 million, (USD 60 million) but also
borrowed a whopping Rs. 2.2 billion (USD 206
million) from a private bank to fund the
multi billion rupee Combined Cycle Power
Plant at Kerawalapitiya.
Laxapana
In this case, the Power and Energy Ministry
fiddling with yet another power project
pushed for a multi billion rupee contract
with a German hydro power manufacturer which
has jumped estimates by over Rs. 2 billion.
Against all norms of tender procedures and
national procurement agency guidelines the
Ministry chose to get a single source
proposal from VOITH Siemens to rehabilitate
Old Laxapana for a price that is
approximately 64% higher than the estimated
cost. In rupee terms the difference in cost
amounts to over Rs.2 billion.
The price received by the Ministry for the
project from Voith Siemens (after the
discount) is approximately Euro 25.8
million. However, the Technical Evaluation
Committee (TEC) is of the view that the cost
of rehabilitation should be in the range of
Euro 17.2 - 18.5 million. In fact, the TEC
advised the Cabinet Appointed Negotiating
Committee (CANC) that VOITH Siemens price is
53% - 64% higher than the estimated cost.
Estimates were arrived at based on a study
done by the Japanese International
Cooperation Agency (JICA).
Voith Siemens is also not the original
equipment manufacturer of the Old Laxapana
Power Station.
The Old Laxapana Hydro Power Complex
comprises of a hydro power plant of 25MW
commissioned in the early 1950s,
Wimalasurendra Hydro power plant of 50MW
commissioned in the early 1960s and the New
Laxapana Hydro Power Plant of 100MW
commissioned in the early 1970s. It is the
first hydro power complex in Sri Lanka which
provides an annual average energy supply of
1432 Gwh.
Due to the obsoleteness of these three
plants, reliability has become an issue.
Maintenance of the plants has become
difficult and expensive. Which is why, a
study done by the Japanese International
Cooperation Agency identified urgent and
major rehabilitation needs.
Galle power project
Meanwhile reproduced below is a letter
addressed to the Minister of Power and
Energy W.D.J. Seneviratne by Head of
Mission, Embassy of Sweden, Borje Mattsson
pointing out a conflict of interest in
deciding an award of tender. The letter and
the sequence of events below speak for
themselves.
Embassy of Sweden Colombo
22 October, 2008
Hon. W.D. J. Seneviratne
Minister of Power & Energy, Ministry of
Power & Energy, Government of the Democratic
Socialist Republic of Sri Lanka.
Re: New Galle Development Project, Ceylon
Electricity Board
Lot A: Construction of a 3x31.5 MVA 132/33kV
Grid Substation at Galle
The Swedish Embassy in Colombo has been
informed by AREVA T&D, a Swedish Company,
that the said company has made a
representation regarding the captioned
project to the Procurement Appeal Board in a
letter dated 16th October and copied to you
Hon. Minister. (I attach the copy for your
ready reference).
The project is financed by the Nordic
Investment Bank (NIB). In the appeal AREVA
T&D raises a number of issues against the
recommendation of the Cabinet Approved
Negotiation Committee (CANC).
Among the issues raised by AREVA T&D are:
Item No. 2 in Annexure 3 of the
representation referring to "Bidder shall be
preferably from the NORDIC/BALTIC countries.
If the bidder is not from NORDIC/BALTIC
countries the main part of the supplies (not
less than 50% of content) need to be sourced
in the NORDIC/BALTIC countries.
NORDIC/BALTIC countries are Norway, Sweden,
Finland, Denmark, Estonia, Iceland, Latvia
and Lithuania." And Item No. 3 in Appendix 3
of the representation "Lanka Transformers
Limited is a subsidiary of Ceylon
Electricity Board (CEB, the Employer) with
CEB having the majority of 63% and thus
should issue the Parent Company Guarantee.
This is a clear conflict of interest."
With this letter I would like to draw your
Ministry's attention to AREVA T&D's
representation to the Procurement Appeal
Board.
Yours sincerely
Borje Mattsson
Head of Mission
Embassy of Sweden
This three billion rupee project hangs in
the balance with billions of rupees pledged
by a foreign investment bank to the
government on hold in the backdrop of a
possible scam.
The project is to be funded by the Nordic
Investment Bank. Tenders were invited by
notice published last year on June 19. The
closing date for bids was September 17,
2008.
The Procurement Committee (PC) having
evaluated the bids received recommended to
the CANC the award of the tender to Lanka
Transformers Limited (LTL). The report of
the PC stated that the LTL bid was in
conformity with all tender conditions and
specifications. Accordingly the CANC
recommended the award of the tender to LTL.
The procedure with regard to tender awards
require that the concerned Ministry should
inform all unsuccessful bidders of the
decision of the CANC to award the tender to
the selected bidder and for the unsuccessful
bidders to submit appeals, if any, to the
Procurement Appeal Board (PAB) set up in the
Presidential Secretariat, within seven days
of the date of letter.
Informed the unsuccessful bidders
J. M. K. Jayasekera in this instance too in
his capacity as Senior Assistant Secretary
(Tenders) of the Ministry of Power & Energy
by his letter dated October 3, 2008 informed
the unsuccessful bidders of the
recommendation of the CANC to award the
tender to LTL. This letter however was
received by unsuccessful bidders only on
October 15, 12 days after it was signed on
the 3rd.
The unsuccessful bidders responded to these
letters stating that they were received only
on October 15 and that they would submit
their objections to this recommendation to
the PAB within seven days ending October 22,
2008. Their main objection was that LTL was
not in conformity with tender conditions and
specifications.
Having considered the appeals of all
unsuccessful bidders, The Procurement Appeal
Board informed the cabinet of ministers that
it rejects the recommendation of the CANC to
award the tender to LTL as LTL is ineligible
to bid at this tender and therefore the bid
is unresponsive.
The PAB amongst many shortcomings found that
LTL being a subsidiary/affiliate of the CEB
is not eligible to bid in this tender in
terms of Section 8 of Volume 5 of Tender
Conditions. The CEB holds a share of 63% in
LTL.
Also that LTL has not met the minimum
requirement of Nordic/Baltic input in excess
of 50% in terms of Clause 3 and 4 of Section
1 of Volume 1, Instructions to Bidders.
That the 31.5MVA power transformers offered
in Lot A and ACSR Zebra Conductor offered in
Lot B by LTL are not in conformity with the
tender specifications and requirements.
Not in conformity
Most importantly, LTL did not have at the
time of the tender closing on September 17,
2008 the ISO 9001:2000 certificate for the
scope of work of the project (Lot A and B)
which is mandatory under the tender
conditions.
The PAB also recommended to the Cabinet of
Ministers to direct the CANC to add two
independent and competent officials
unconnected to the CEB to the Procurement
Committee and to consider the bids received
with the assistance of the PC and to make a
suitable recommendation.
This the cabinet of ministers on November
19, 2008 agreed to do with the
recommendations of the PAB and directed the
Ministry to take action in terms of the PAB
recommendations.
However LTL on December 1, 2008 filed a
fundamental rights (FR) application under
Articles 17 and 126 of the Constitution of
Sri Lanka that its fundamental rights had
been violated by the directive of the
cabinet of ministers on the recommendation
of the PAB.
This FR application was called before the
Supreme Court (SC) on December 4, 2008, and
the court ordered the suspension of the
decision of the cabinet giving effect to the
recommendations of the PAB and directed the
secretary to the Ministry to take steps to
award the tender to LTL, calling on the
respondents at the same time to file answers
within four weeks, with LTL counter
affidavit to be filed two weeks thereafter.
Does not conform to specifications
Meanwhile in view of the controversy and the
fact that LTL indeed does not conform to
specifications indicated in the bid document
including conditions stated by the funder
Nordic Investment Bank - the bank, The
Sunday Leader learns has indicated that it
is considering withdrawing the pledged
funding of Rs.3 billion to the government.
The Supreme Court in its order of 4.12.2008
has stayed the cabinet decisions on an
application made by LTL and directed that
steps be taken to award the tenders to LTL.
Meanwhile the Nordic Investment Bank Board
is to meet later this month with this fresh
information and decide on the procedures to
be adopted in taking this project forward
since it has been delayed for more than two
years..
|
Lanka Transformers Limited (LTL).
The share issue of Lanka Transformers
Limited is
10,500,000 - Shares owned by CEB
1,670,000 - Owned by Lanka Transformers
Group Share Ownership Trust
4,500,000 - Owned by LTL ESOT Limited
63% of Lanka Transformers Limited is owned
by the CEB. However almost all engineering
work that is undertaken with the CEB is
executed by LTL Projects (Private) Limited
which is a 100% privately owned company
belonging to U.D. Jayawardena, the CEO of
Lanka Transformers Limited and other
directors of Lanka Transformers Limited.
LTL ESOT Limited owns 4,500,000 shares of
Lanka Transformers Limited and this company
is a private entity. According to Form 15 of
this company the directors of LTL ESOT are
as follows, (They all are working or have
worked at Lanka Transformers Limited).
U.D. Jayawardena, M.J.M.N. Marikkar, R.K.
Pitigalage, W.D.A.S. Wijayapala, D.A.J.
Nanayakkara, S. Annasiwatta, K.B.M.I. Perera.
Though the CEB is the major shareholder of
LTL (63% owned by the CEB) it appears LTL
Projects (Private) Limited, the privately
owned company of the CEO and other members
of LTL are making money through the
engineering works the profits of which do
not accrue to the CEB. |