|
Unbridled spending by government
|

The US $ 430 million loan for the construction of
the Kerawalapitiya power plant was provided only
on the
basis of a government guarantee of the funds — and
without any long term analysis of the viability of
the project |
By R. Wijewardene
Ambitious new development projects are rapidly changing
the face of this country.
A
series of spectacular schemes – the port at Hambantota,
the power plants at Norochcholai and Sampur, the
Southern Expressway will, it is envisaged, establish the
infrastructural base on which the country’s future
economic growth will be built.
However while rapid infrastructure development and such
large scale investment in the country’s future is an
encouraging and welcome sign — the finances behind these
schemes — precisely how a fundamentally bankrupt
government is raising the billions it needs to implement
these projects is an open and troubling question.
For
the most part these various mega project are government
to government development aid schemes, i.e. they are
being bankrolled by ‘friendly’ nations — China and Iran
in particular and in some cases India, not as grants.
Loans not grants
However while foreign governments are providing the
funds and expertise required to implement these projects
it’s necessary to understand that the funds for the
implantation of these schemes are being supplied not as
grants but as loans.
Sri Lanka
now owes the Chinese and Iranian governments billions
for the assistance they have provided and interest will
have to paid on these enormous sums of borrowed money.
The
money being spent by China and Iran today will have to
be paid back by
Sri Lanka —
tax paying Sri Lankans — in the future and a
confidential report in the possession of The Sunday
Leader raises questions about the viability of the
government’s current rash of spending.
The
report argues that far from bringing development many of
these much vaunted new infrastructure projects will
produce only impractical white elephants — expensive
failures that the nation’s population will be paying for
decades to come.
Misdirected and excessive spending
The
report singles out the Kerawalapitiya power plant, the
Uma Oya project and plans for the Iranian funded
expansion of Sri Lanka’ oil refining capacity as
examples of misdirected and excessive spending.
The US
$ 430 million loan for the construction of the power
plant was provided only on the basis of a government
guarantee of the funds — and without any long term
analysis of the viability of the plant project.
Initially it had been estimated the project would cost
only $300 million.
However despite the enormous cost the plant generates
only 200 megawatts of power, rather than 300 megawatts
it was scheduled to deliver.
Further as the plant uses a high cost fuel, electricity
generated by the plant is sold by the CEB at a massive
loss amounting to Rs. 5000 million or $ 50 million a
year — an astounding figure.
These
losses could have been avoided if the correct
feasibility studies had been conducted. However the
loans that financed the project were supplied before any
such studies were completed.
Differed radically
Extraordinarily the cabinet initially approved the
project on the basis that it would utilise a low cost
fuel. However the ready availability of funding prompted
contractors to embark on a project that differed
radically from the one originally approved.
The
end result of all this spending however was a white
elephant, a power plant that was $120 million over
budget, but generating less electricity than it is
required to and which continues to incur enormous
losses.
The
argument encapsulated in the Kerawalapitiya case is that
as these major development projects are funded not by
any sort of commercial interest, but by government to
government loans, very little thought has been given to
the long term financial viability of the schemes.
When
projects are funded by banks, or international lending
agencies — ADB, World Bank etc., the money lent is
contingent on the viability of the scheme. In order to
secure funding from development banks the government
must provide analyses that indicate the project is
likely to be a success and generate the revenue needed
to finance repayments.
No assessment of the viability
However where the government’s current mega projects are
concerned very large amounts of money have been made
available with almost no assessment of the viability of
the projects concerned.
China
and Iran both keen on winning allies and flushed with
money from economic growth and oil booms are not careful
about their lending and the government apparently unable
to resist the vast amounts of cash on offer has been
profligate with its spending.
With
all the projects currently underway the government’s
debt burden is now significant with over $ 3 billion for
the Kerawalapitiya, Uma Oya and refinery expansion
projects and precisely how this money will be repaid is
now a pressing issue.
It is
of course hoped that the revenue generated by these mega
projects — irrigation schemes, refining projects etc.,
will allow them to pay for themselves. However in most
cases the expenditure on these projects greatly exceeds
independent estimates of the projects’ earning
potential.
Government spending $340 more
In the
case of the proposed Uma Oya hydro-power and irrigation
scheme, Iran has undertaken to provide over $500 million
to implement the project. However initial estimates by
the CEB for constructing the relevant damn and channels
placed the cost of the scheme at a mere $160 million.
By
agreeing to accept $500 million of Iranian financing the
government is spending $340 more that its own estimates
suggested should be the real cost of the project.
Whether the revenue generated from the Uma Oya will
ever justify such massive expenditure is open to
question.
The
project is notoriously fraught with environmental
hazards. Leading environmentalists doubt that the
watershed of the Uma Oya is large enough to support such
a large scheme.
As the
Uma Oya has already been diverted and tapped for
irrigation at several points, environmentalist have
suggested that instead of irrigating more land the
project will precipitate droughts in areas further
upstream.
No
major studies appear to support the government’s claim
that the scheme will irrigate 25,000 acres of land.
Frightening lack of analysis
Ultimately, despite a frightening lack of analysis —
given the scale of the environmental and economic
implications of the project — the Uma Oya scheme has
already been approved. Again the government seems unable
to resist the large sums of money proffered by its
allies. However in every case it must be remembered that
these funds are provided as loans rather than grants.
The
Uma Oya scheme is potentially an ecological and
financial disaster. Even more unviable appears to be,
the ambitious and more expensive Iranian scheme to
expand the country’s oil refining capacity by 50,000
barrels a day.
In
this case
Iran
has undertaken to provide a $1.5 billion loan to install
the relevant refining equipment tank facilities etc.
Once again, no feasibility studies have been conducted
to ascertain whether or not
Sri Lanka
requires such a large expansion of its refining
capacity.
Also
the CPC’s initial estimates for the cost of a
50,000-barrel increase in its refining capacity was $
500 million. The government is currently borrowing $1.5
billion to implement the scheme.
The
lure of easy money it seems has persuaded the government
to spend over $1 billion over the odds for a project the
country does not need. Interest payment on the $ 1.5
billion loan would amount to hundreds of millions of
rupees per year and whether the country would genuinely
earn significant revenue from this expansion in its
refining capacity is open to question.
Enormousunnecessary debts
The
nation therefore is being saddled with enormous
unnecessary debts and the government appears to be
knowingly entering into overvalued deals, which can only
raise the spectre of massive corruption.
In
every case the fundamental problem appears to be the
absence of safeguards. With
China
and Iran eager to provide funds the relevant studies and
procedures to ascertain the viability and necessity of
the projects are not being carried out.
Cash
flow analyses and environment impact assessments are
being dismissed in the government’s eagerness to seize
the cash on offer.
The
end result however is that the government of a country
whose entire foreign reserves consist of an IMF loan is
now accruing billions of dollars of additional debt.
How
the interest and principle of these loans will
eventually be paid back is a troubling question but what
is certain is that the taxpayers of this country will
bear the burden of these repayment well into the next
decade.
 |